The construction process for the ITALGRIP® System has four phases.
The system can be applied in various widths and in the presence of traffic.

1

Cleaning the existing pavement
Clean deposits of dust, road oils, gasoline, etc., from road surface.
 

2

Apply the resin
Using a special spray truck, a specific quantity of resin (lb/sq. ft.) is applied according to surface characteristics of the pavement.
 

3

Apply the Aggregate
Using a conventional chip-spreader, the aggregate (MC-1) is applied immediately after the resin is applied.
 

4

Remove excess aggregate
After the resin hardens (2 – 4 hours) the excess aggregate is removed using a vacuum sweeper.
 

The formulation of the epoxy binder and the on-board computer controls assure a continuous and uniform application. The time to reopening the road to traffic is greatly reduced.

The maximum amount of ITALGRIP® the equipment can place in one sixteen-hour day is 15,000 lineal feet.


 



  video clip
video of the application

The link opens a new window with a video clip showing the construction process.

 video
Format:
Windows Media Video
Version 9
1,31 Mb


italgrip home page Italgrip USA, Inc.
N2553 Smith Rd.
Lodi, WI 53555
Phone: (608) 592-2725
Fax: (608) 592-2516
Cell: (608) 698-1712
home page

top